1st class powdercoating
PRE-TREATMENT
Our chemical immersion system ensures the base metal is properly treated and ready for the Powdercoating Process
1st Process
Degreasing Tank
This is an alkaline immersion degreaser formulated to remove oils and contaminants from either ferrous or non-ferrous metals. This tank is also heated to 55 Degrees Celsius for ultimate performance.
2nd Process
Clean Water rinse
Between each treatment we use a clean fresh water rinse to neutralise any leftover residue/contaminants from the previous treatment.
3rd Process
Iron Phosphate
Iron phosphate immersion tank that achieves better adhesion and corrosion resistance - achieving up to 1000 hours Salt Spray testing.
This tank is also heated to 45Degrees Celsius for optimum treatment.
4th Process
Clean water Rinse
Between each treatment we use a clean fresh water rinse to neutralise any leftover residue/contaminants from the previous treatment.
5th Process
Chrome Sealer
Our chrome sealer is used in our immersion tank to improve paint adhesion, minimise under-film corrosion and blistering on iron phosphate conversion coatings.
Immersion Tanks Specs
The tanks themselves will accept product up to 2900mm Long x 1200mm Wide x 1300mm High
Custom Preparation
For any product larger than our tank sizes, we offer a pretreatment procedure that provides outstanding results.